Detroit-Superior Bridge
Detroit-Superior Bridge
ClevelandPrimary Service
- Surveying
Client
- Sub-Consultant to Pennoni for ODOT D-12
Location
- Cleveland
Tasks Performed
- Surveying
- Mapping
- Right-of-Way Easements
Project Description
The project included superstructure and substructure repairs to the 15-span, 2,880 foot long historic Detroit-Superior Bridge. Euthenics’ role on the project was to provide the survey and mapping and prepare right-of-way plans for this major bridge rehabilitation project. Survey was performed in accordance with the Ohio Department of Transportation’s Survey and Mapping Specifications. A total of nine temporary easements were obtained for the repair work areas. Title reports and record documents were obtained from the Cuyahoga County Records and analyzed. Utilizing the data obtained from the boundary survey, the location of property lines, existing right-of-way, and utility easements were determined. Our survey team worked closely with the bridge designer to ensure our work complimented theirs and project deadlines were met.